Staged, live-site boiler-house refurbishment: new boiler plant installed alongside the existing to maintain continuous heating & hot water, avoiding temporary hire plant and enabling a clean changeover.

The ITT envisaged swapping out the existing boilers via temporary hired gas plant to keep the school running. We proposed a parallel installation strategy instead: keep the existing boiler plant in place and operational while the new equipment is installed and commissioned.

Once the new boilers were proven, we transferred heat and hot-water production to the new plant and then decommissioned the legacy equipment  delivering the upgrade without disrupting school life.

  • Approach: Parallel install & staged changeover (no temporary hire plant)
  • Scope: Live boiler-house refurbishment, commissioning and controlled cut-over
  • Outcome: Zero downtime, reduced risk & cost, modernised plant ready for future operations